Butte, Montana, stands at the headwaters of the Clark
Fork
River and has been a center of extensive underground mining since about
the 1870s. Open-pit mining began at the Berkeley Pit in 1955 and continued at
the Continental Pit until its closure in June 2000. As part of the underground
mining activities, ground-water levels had to be continually lowered
as mining went deeper. When underground mining finally ended (1975),
the workings included over 49 miles of vertical shafts and over 5,600
miles of horizontal workways.The Anaconda Company estimated there were
over 10,000 miles of workings when all other passages were included.
As early as 1901, ground water encountered in Anaconda Copper Mining
Company properties was drained to a common mine level for pumping to
the surface. Water drainage was through interconnected stopes, drifts,
or diamond-drill drainage holes that were used to transport water to
the central pump stations. By the 1910s, as many as 28 mines were dewatered
this way. The pumped mine water contained sufficient quantities of dissolved
copper sulfate that it was directed to precipitation plants for copper
recovery. Larger
Image

The Berkeley Pit, an open-pit
copper mine, was dewatered through the underground mine dewatering
system. The Atlantic Richfield Company (ARCO) bought the Anaconda Company
in 1977 and continued to operate the underground pumping system until
April 1982, when the decision was made to suspend mining in the Berkeley
Pit. The pump station, located on the 3,900 level (3,600 feet below
ground surface) of the Kelley Mine, was shut down, and ground-water
levels began to rise immediately. Levels had risen more than 1,300
feet by the end of 1982 and 3,100 feet by the end of 2006. The maximum
elevation (5,410 feet) that water levels will be allowed to reach in
the underground workings and Berkeley Pit has been established by U.S.
Environmental Protection Agency (EPA) and the Montana Department of Environmental
Quality (DEQ) in order to maintain the Berkeley Pit as a "Terminal
Pit."
The Butte underground mines and the Berkeley Pit
are part of a Federal Superfund Site. A long-term monitoring program
was established to ensure that the Berkeley Pit remains the sink, or
terminal pit, for bedrock ground water entering and filling the historic
mine workings. This closed system would preclude mine-water discharge
to nearby aquifers and surface waters.
To date, the Butte
Mine-Flooding monitoring network maintained by the Montana Bureau of
Mines and Geology (MBMG), Montana Resources (MR), and ARCO consists
of:
- 70 ground-water monitoring sites (wells and mine shafts),
15 of which are equipped with continuous water-level recorders;
- two surface-water gauging stations;
- a database that contains over 2,000 complete water-quality analyses
that were collected from surface-water, ground-water and mine-shaft
locations;
- and 25 years of monitoring data, i.e., water levels and flow.
The water in the Berkeley Pit is highly acidic and high in concentrations
of arsenic, copper, cadmium, cobalt, iron, manganese, zinc, and sulfate,
plus other inorganic constituents. Water-quality samples are collected
semi-annually at selected locations. Water quality in the underground
mines was very acidic and high in metals concentrations when flooding
began; however, as water levels have risen, pH has increased and metals
concentrations have decreased.
Flooding of open-pit mines is ongoing at numerous abandoned mines worldwide.
The water in individual pits ranges from highly acidic and containing
high concentrations of heavy metals, to moderately alkaline with little
or no water-quality contamination. The deep water of the pit lake - the
hypolimnion - is separated from the shallow water - the epilimnion - by
a chemocline. A chemocline is a zone of rapid chemical and physical change;
in the Berkelely Pit Lake, the chemocline is between 35 to 50 feet below
the lake surface. The hypolimnion is characterized by pH of 2.5; temperature
of 4.5 °C; specific conductance of 8,600 µS; redox of 630 mV; and turbidity
of 5 NTU. Dissolved-metal concentrations in the hypolimnion include Cu,
190 mg/L; and Zn, 620 mg/L. The epilimnion is characterized by a pH of
2.5; temperature of 0 °C in winter (ice forms on the surface) to 25 °C
in summer; specific conductance of 7,900 µS;
redox of 670 mV; and turbidity of 30 NTU. Dissolved-metal concentrations
in the epilimnion include Cu, 140 mg/L; and Zn, 540 mg/L. Iron(II):Iron(III)
ratio in the hypolimnion is 2.5 and in the epilimnion 0.36.
To better understand the water chemistry and its changes in these pits,
an understanding of the ground-water flow system is necessary. The Butte
mines and Berkeley Pit are unique with respect to other flooding open
pits because of the large historic underground mine operations interconnected
with the Berkeley Pit.
Butte
Mine-Flooding Monitoring Summary
Current
Conditions:
— Berkeley
Pit water level the end of December, 2011 was at elevation 5,299, 111 feet below the critical water level
— 2005
Berkeley Pit infilling model predicts water-level will reach action
level at Anselmo Mine compliance point on June 2021
— 2005
groundwater flow into pit 2.55 mgd
Important
Dates
— 1994 – September,
EPA/DEQ issue Record of Decision (ROD) for Butte Mine-Flooding Operable
Unit.
— 1996 – April,
MR and ARCO divert Horseshoe Bend (HSB) drainage water away from Berkeley
Pit to slow filling rate, per ROD.
— 2000 – July,
MR suspends mining operations due to high energy costs, HSB water allowed
to flow back into pit, increasing pit filling rate.
— 2002 – March,
USEPA and Montana Department of Environmental Quality (MDEQ) enter
into a Consent Decree with BP/ARCO and the Montana Resources Group
(known as the Settling Defendants) for settlement of past and future
costs for this site.
— 2002 – Fall,
SUEPA and MDEQ issue order for Settling Defendants to begin design
of water treatment plant for HSB water. Settling Defendants issue contract
and begin construction of treatment plant.
— 2003 – November,
MR resumes mining operations.
— 2003 – November
17, HSB water treatment plant comes on line slowing pit filling rate.
General
Observations:
— Montana
Resources (MR) suspension of mining operations in the Continental Pit
(June 30, 2000) continued through mid-November 2003 when mining resumed.
This suspension has allowed water from the Horseshoe Bend Drainage
to once again flow unchecked into the Berkeley Pit. Since April 1996
MR has been using this water in their mining operation, keeping it
out of the Pit.
— The average
flow rate from July 2000 through November 2003 was 1,820 gpm. This
resulted in an additional 3.35 billion gallons of water entering the
Berkeley Pit. This input approximately doubled the monthly filling
rate.
— The Berkeley
Pit water level rose 7.69 feet in 2006, to an elevation* of 5,264
feet.
— Depth
to water as measured in the Kelley Mine shaft on December 2006 is
628 feet, which is an elevation of 5,276 feet.
— The East
Camp System bedrock water level is 30 to 320 feet below the approximate
bedrock-alluvial contact, which varies from an elevation of 5,259
to 5,550 feet on the eastside of the Pit.
— Water levels
in the East Camp Mine/bedrock system rose between seven to nine feet
in 2006.
— Water
levels in the West Camp Mine System rose or declined one to two feet
during 2006. West Camp mine water levels were controlled by pumping
at the West Camp pumping well. Over 290 acre-feet of water was pumped
during 2006.
— Since the
cessation of pumping in the underground mine workings by ARCO on April
23, 1982, water levels have risen over 3,100 feet in the East Camp
Mine/bedrock system and over 230 feet in the West Camp Mine/bedrock
system.
— The water in
the Berkeley Pit is over 900 feet deep.
— The Horseshoe
Bend Drainage surface water diversion implemented April 1996 was
successful in keeping up to 3,000 gallons per minute of surface
water from flowing into the Berkeley Pit. Note this diversion was
discontinued June 30, 2000, allowing this water to flow into the
Pit. However, following the completion of the water treatment plant,
this water is no longer entering the pit.
— Water
quality in the Berkeley Pit changes with depth. Copper varies from 178
ppm to 187 ppm while arsenic concentrations vary from 0.21 ppm
to 2.00 ppm from 3 feet to 200 feet deep.
Summary
of Record of Decision (ROD) Butte Mine-Flooding Operable Unit
The Butte
Mine-Flooding Operable Unit (OU) is one of four OUs
within the Butte Mining district (BMD) and consists of approximately
23 square miles. The OU
is
divided into two systems: 1) East Camp/Berkeley Pit, and 2)
West Camp. Other OUs in the BMD are the Butte Priority Soils,
Silver Bow Creek/Streamside Tailings, and Non-Priority Soils.
Major
features of the OU are
1) underground mine workings, 2) Berkeley Pit, and 3) alluvial
and bedrock aquifers contributing flow to the system.
Berkeley
Pit is
the most prominent feature of the OU; it is 1,780 feet deep and
occupies 675 acres. It is approximately 1½ miles across,
East to West, and one mile across, North to South. In 1994 it contained
approximately 26 billion gallons of acidic water (pH<3.0). (2006
estimates are over 37 billion gallons of water.)
Water inflow to the Pit (1994)
is approximately 5,000 gallons per minute (gpm), or 7.2 million
gallons per day (mgd). Approximately 1,500 gpm (2.16 mgd) comes
from surface water draining into the pit, while 3,500 gpm (5.04
mgd) comes from ground water (combination of alluvial and bedrock
system).
Record of
Decision specifies the following:
- Permanent
control and treatment of 1,700 gpm (2.4 mgd) of Horseshoe Bend
drainage water, or other appropriate source.
- Treatment
of surface water; it can be incorporated into current mining
operations, or treated for discharge.
- 24
months prior to projected MR mine closure, or when the water
level in the pit system reaches an elevation** of
5,260 feet, a focused review of treatment technologies will be
conducted.
- Upon suspension of mining, all contaminated surface-water flows
shall be captured and treated. Alternative inflows will be considered,
but must treat a minimum of 1,700 gpm (2.4 mgd). All uncontaminated
surface waters will be diverted around East Camp/Berkeley Pit
system.
- Water
levels in the East Camp/Berkeley Pit system will not be allowed
to exceed the established Safe Water Level (SWL) of 5,410 feet;
while water levels in the West Camp System will not be allowed
to exceed 5,435 feet. The water level in the East Camp will be
kept below that of the West Camp.
- Within
eight years of approaching the SWL, design of final water-treatment
plant shall begin, with construction completed four years prior
to the projected date for water to reach SWL. This will allow
for a shake-down period, for optimizing plant operations.
- Long-term,
ground-water and surface-water monitoring program will be implemented.
- Establishment
of a community education and information dissemination program.
*Note See
September 29, 1994 Record of Decision for complete
description of selected remedy. Conditions are those
described in ROD
** Elevation datum
is USGS